- Testing and Commissioning of GIS up to 400kV.
- Testing and commissioning of Switch Yard up to 400kV.
- Testing and commissioning of LT & MV Switch gears.
- Testing and commissioning of LT & MV Motors and Drives
- Testing and commissioning of Distribution & Power Transformers.
- Testing and commissioning of Generator AVR.
- Transformer Differential Stability, Generator Stability, Overall stability, Busbar
Stability, Motor Differential Stability, Line Differential, End to End test & etc… - Testing and commissioning of Electro mechanical, Static & Numerical Relays.
- Trouble shooting of Switch gears, Switch Yards, Power Plants, Process Plants & etc.
- Insulation Resistance measurement.
- Winding Resistance measurement.
- Turns Ratio measurement.
- Tan Delta & Capacitance measurement.
- Contact Resistance using micrometer.
- Dynamic Contact Resistance measurement.
- Short Circuit impedance measurement
- No load loss measurement (open circuit test).
- Power Factor Measurement.
- Breaker Timing measurement
- Testing & commissioning of Electro mechanical, Static relays and Configuration,
- Testing & commissioning of Numerical relays.
- LCM (Leakage current measurement).
- Battery & Battery charger testing and commissioning.
- Partial Discharge test.
- Sweep Frequency Response Analysis (SFRA) test
- Thermo vision – Temperature measurement at live conductor’s joints.
- Harmonic analysis.
- Power line carrier communication.